Contracts Overview

A contract establishes the legal obligation for one party to pay another a certain amount of money for a specific scope of work to be performed. In a construction contract, the scope of work is delineated in text, but is also expressed by the contract documents, which are the drawings and specifications that describe the construction project. A contract is based on specific revisions of the contract documents. 

A contract is legally enforceable once it has been executed (signed) by a legitimate representative of each contracting party. The executed copy of the contract is very important for both companies to retain.

        A prime contract is a contract where a company receives payment for their services. This is typically between the owner and the general contractor or architect. 

        Subcontracts and purchase orders (POs) are contracts between a company and the companies they need to pay (for example, general contractoràsubcontractor/supplier, or architectàconsultant). 

        Change orders (COs) are legal changes to the original contract. COs may:

  • Add, subtract, or have no impact on the dollar amount of the contract;

  • Add or delete work from the subcontractor's responsibility;

  • Be used to officially bind the subcontractor to revised drawings or specifications;

  • Change the total amount of time the subcontractor has to perform the work.

The overall process of bidding and awarding subcontracts/POs is called “project buyout.” A project is considered “100% bought out” when all major subcontracts/POs have been awarded. This phase can easily take 3-4 months in total. 

Some earlier subcontracts (like surveying or sitework) will be released to start work on the jobsite before the later subcontracts (drywall, interiors, accessories) are awarded. Project management and estimating work together to prioritize the order of the buyout, taking into account information such as when the subcontractor is required on the jobsite and manufacturing/delivery time of long lead-time items (structural steel, HVAC equipment, etc).

Info Exchange support

Contracts can be reviewed and sent electronically through email or Info Exchange. From Info Exchange, external project team members can do the following:

        Track contracts items that are assigned to you.

        Respond to contract items assigned to you.

        View baseline commitment value for subcontracts, which forms the foundation for change order tracking and forecasting. 

        View cost code-level of detail for contract commitments.        

 

Your ability to view all contracts depends on your permission set assignment.

 

Commitments workflow

 

Related Topics

Contract Log

Contract page

My Contract Actions log

My Expected Contracts log

 

 

 

Table of Contents

Index

Search (English only)

Back